Project Sunrise flight testing weeks away but launch pushed back

qantas
Delivery of the new Airbus a350-1000s has been pushed back until November 2027.

The launch of Qantas’ new non-stop services from the East Coast of Australia to New York and London has been pushed back into late 2027 due to supply issues.

Dubbed Project Sunrise, the first of the new Airbus planes are just weeks away from flight tests after rolling off the production line in Toulouse.

While the first plane is on track to be delivered by April 2027, supply chain issues have pushed back the remainder of the order until November.

“Preparations for Project Sunrise continue with the first Airbus A350-1000ULR now in the paint shop in Toulouse taking on its Qantas livery, and test flights just weeks away,” a Qantas spokesperson said.

“Pilot training is well underway at our new A350 simulator in Sydney, and next month we’ll announce the first route and timing of our inaugural commercial services.

“Qantas ordered 12 A350-1000ULRs in May 2022, which will operate the first non-stop services from the East Coast of Australia to New York and London. When these services take off, passengers will save up to four hours off the journey. Three aircraft are needed to run a daily non-stop service on either route.

“While the first aircraft delivery has shifted to April 2027, the next four will follow in quick succession, putting us back on our original schedule by November.

“We continue to work closely with Airbus on the delivery and certification process that will enable us to begin operating these history-making ultra long-haul flights.”